Risk Assessment of Solar Power Plant Development in Indonesia Using The Analytic Hierarchy Process Method
DOI:
https://doi.org/10.62146/ijecbe.v3i3.110Keywords:
Solar Power Plant, Risk Management, Analytical Hierarchy ProcessAbstract
The Ministry of Energy and Mineral Resources is committed to building Solar Power Plant in Indonesia with the aim of increasing the national electrification ratio and ensuring equitable energy access, especially for people who have not enjoyed electricity. This study aims to determine what risk factors exist in the construction of Solar Power Plant and conduct a risk assessment using the Analytic Hierarchy Process (AHP) method. The results of the analysis show that there are 7 criteria and 38 risk sub-criteria. The project risk criterion has the highest weight with an expert value of 25.2%, self-assessment 36.9% and employees 2.2%. In the sub-criteria, the provider is late in completing the work, it has the highest weight with an expert value of 6.7%, self-assessment 10.6% and employees 0.1%.
References
Undang-Undang Nomor 30 Tahun 2007, tentang Energi.
Kementerian ESDM, “Data EBTKE,” www.bukusaku.esdm.go.id.
Samsurizal, K. T. Mauriraya, M. Fikri, N. Pasra, and Christiono, “Pengenalan Pembangkit Listrik Tenaga Surya (PLTS),” 2021.
B. Rudiyanto, R. E. Rachmanita, and A. Budiprasojo, Dasar-Dasar Pemasangan Panel Surya. 2023. [Online]. Available: https://sipora.polije.ac.id/27973/2/ebook panel surya.pdf
Peraturan Menteri ESDM Nomor 12 Tahun 2018, tentang Perubahan Atas Peraturan Menteri Energi Dan Sumber Daya Mineral Nomor 39 Tahun 2017 Tentang Pelaksanaan Kegiatan Fisik Pemanfaatan Energi Baru Dan Energi Terbarukan Serta Konservasi Energi.
Peraturan Presiden Nomor 12 Tahun 2021, tentang Perubahan Atas Peraturan Presiden Nomor 16 Tahun 2018 Tentang Pengadaan Barang/Jasa Pemerintah. 2021.
Badan Standardisasi Nasional, Manajemen Risiko Berbasis SNI ISO 31000. 2018.
Project Management Institute, PMBOK® Guide Sixth Edition (PMI, 2017), vol. 6. 2017. [Online]. Available: http://www.citeulike.org/group/14887/article/9008974
AS/NZS 4360, “Risk Management Guidelines Companion to AS/NZS 4360:2004,” Stand. Aust. New Zeal., vol. 10, no. 5, pp. 31–31, 2004.
S. & HCCA, “Compliance risk management : applying the COSO ERM framework,” 2020.
Asosiasi Auditor Intern Pemerintah Indonesia, tentang Standar Audit Intern Pemerintah Indonesia. 2021.
Badan Standardisasi Nasional, “Manajemen risiko SNI IEC/ISO 31010:2016,” Manaj. risiko, pp. 1–187, 2017, [Online]. Available: https://repository.crmsindonesia.org/bitstream/123456789
B. Priyopradono, “Multiple Criteria Decision Analysis Menggunakan Additive Ratio Assessment Pada Pemilihan Uninterruptible Power Supply (UPS),” Insearch Inf. Syst. Res. J., vol. 2, no. 02, pp. 55–63, 2022, doi: 10.15548/isrj.v2i02.4360.
R. Jaya, “Implementasi Multi Criteria Decision Making (Mcdm) Pada Agroindustri: Suatu Telaah Literatur,” J. Teknol. Ind. Pertan., no. October, pp. 234–343, 2020, doi: 10.24961/j.tek.ind.pert.2020.30.2.234.
F. S. Hillier, C. C. Price, and S. F. Austin, 76-Models , Methods , Concepts & Applications of the Analytic Hierarchy Process Second Edition, vol. 175.
M. Huda, K. Okajima, and K. Suzuki, “Identifying public and experts perspectives towards large-scale solar PV system using analytic hierarchy process,” Energy Procedia, vol. 142, pp. 2554–2560, 2017, doi: 10.1016/j.egypro.2017.12.091.
A. Supriadi, A. Rustandi, D. H. L. Komarlina, and G. T. Ardiani, Analytical Hierarchy Process (AHP) Teknik Penentuan Strategi Daya Saing Kerajinan Bordir. 2018.
S. A. Syahrani, “Evaluasi Manajemen Risiko Proyek Konstruksi Menggunakan Metode AHP (Studi Kasus PT X),” Universitas Indonesia, 2023.
R. F. A. Eskander, “Risk assessment influencing factors for Arabian construction projects using analytic hierarchy process,” Alexandria Eng. J., vol. 57, no. 4, pp. 4207–4218, 2018, doi: 10.1016/j.aej.2018.10.018.
E. Akusta, A. Ari, and R. Cergibozan, “Barriers to renewable energy investments in Turkiye: A fuzzy AHP approach,” Renew. Energy, vol. 240, no. December 2024, p. 122161, 2025, doi: 10.1016/j.renene.2024.122161.
K. Al-Hubhi, “Application of the AHP in project management,” Int. J. Proj. Manag., vol. 19, no. 1, pp. 19–27, 2001.
Downloads
Published
How to Cite
Issue
Section
License
Copyright (c) 2025 International Journal of Electrical, Computer, and Biomedical Engineering

This work is licensed under a Creative Commons Attribution 4.0 International License.